Lesson 05 · 12 min read
Construction Contracting and Project Delivery
How to contract and deliver construction — selecting contractors, contract types, bidding, change management, schedule control, and managing the build phase to completion.
Construction is where development risk meets reality. Carefully designed plans, optimistic budgets, and tight schedules confront the messiness of building physical structures. Cost overruns, schedule slips, change orders, weather delays, and quality issues can destroy returns on otherwise viable projects. Successful developers understand construction contracting, select contractors carefully, manage the construction phase actively, and protect themselves with the right contract structure.
This lesson covers construction contracting, delivery methods, and how to manage the build phase effectively.
Construction delivery methods
How you organize the design and construction process affects cost, schedule, risk, and quality. Several delivery methods are common — quick comparison:
| Method | Process | Pros | Cons | Best for | |---|---|---|---|---| | Design-Bid-Build (DBB) | Sequential: design → bid → build | Lowest cost potential, owner controls design | Longest schedule, adversarial, change orders | Simple/public projects, complete documents | | Design-Build (DB) | Single entity does both, phases overlap | Fastest, single accountability, constructibility input | Less owner design control, less competitive cost | Speed-critical, owner-builder relationships | | CM at Risk (CMAR/CM-GC) | CM joins early, GMP shifts risk to CM | Cost certainty via GMP, faster, less adversarial | More expensive than DBB, complex contract | Mid-sized commercial — most common active developer choice | | CM as Agent | CM is owner's agent, no construction risk | Max owner control, lower cost (no GC markup) | Owner takes construction risk | Sophisticated owners with construction expertise | | IPD | Owner/designer/contractor share risk in single contract | Strong collaboration, aligned incentives | Complex contracts, few experienced firms | Large, complex projects |
Design-Bid-Build (DBB)
The traditional approach:
- Owner hires architect/engineer to design
- Design is completed
- Owner bids the project to multiple contractors
- Owner selects contractor (usually low bid)
- Contractor builds per the documents
Pros:
- Lowest cost potential (competitive bidding)
- Clear separation of design and construction
- Owner controls design
Cons:
- Longest schedule (sequential)
- Adversarial relationships during construction
- Change orders if documents are incomplete
- Limited contractor input during design
Best for: Simple projects, public projects, projects with complete documents.
Design-Build (DB)
A single entity provides both design and construction:
- Owner hires design-builder
- Design and construction overlap
- Single contract for entire project
Pros:
- Faster (overlapping phases)
- Single point of accountability
- Contractor input during design (constructibility)
- Reduced disputes
Cons:
- Less owner control over design
- Less competitive cost
- Quality dependent on builder
Best for: Projects where speed matters, owner-builder relationships exist.
Construction Manager at Risk (CMAR or CM/GC)
A construction manager joins the team early:
- Owner hires architect
- Owner hires CM during design
- CM provides preconstruction services (cost estimating, constructibility, scheduling)
- CM takes on construction risk via Guaranteed Maximum Price (GMP)
- CM manages construction
Pros:
- Constructibility input during design
- Cost certainty via GMP
- Faster than DBB
- Less adversarial than DBB
- Owner retains design control
Cons:
- More expensive than DBB
- Requires capable CM
- More complex contract structure
Best for: Mid-sized commercial projects, where speed and cost certainty matter.
This is the most common approach for active developer commercial projects.
Construction Manager as Agent
CM acts as owner's agent without taking risk:
- CM provides services for fee
- Owner contracts directly with subcontractors
- CM coordinates and manages
Pros:
- Maximum owner control
- Lower cost (no GC markup)
- Transparency
Cons:
- Owner takes construction risk
- Requires sophisticated owner
- Complex coordination
Best for: Sophisticated owners with construction expertise.
Integrated Project Delivery (IPD)
Owner, designer, and contractor share risk and reward:
- Single contract among multiple parties
- Shared profit pool
- Collaborative decision-making
- Risk shared
Pros:
- Strong collaboration
- Aligned incentives
- Best for complex projects
Cons:
- Complex contracts
- Few firms experienced
- Less common
Best for: Large, complex projects.
Contract types
The contract type determines how the contractor is paid.
Lump sum / fixed price
Contractor agrees to complete the work for a fixed price:
- Risk on contractor for cost overruns
- Owner has cost certainty
- Best for complete documents and well-defined scope
- Most common for commercial development
Variations:
- Lump sum with allowances for items not yet defined
- Lump sum with unit prices for items measured in field
Cost-plus
Contractor is reimbursed for actual costs plus a fee:
- Cost plus fixed fee — fee is a fixed dollar amount
- Cost plus percentage fee — fee is a percentage of costs
- Cost plus with GMP — costs reimbursed up to a guaranteed maximum
Pros:
- Faster start (don't need complete documents)
- Open book (transparent)
- Owner sees true costs
Cons:
- Owner takes cost risk (without GMP)
- Less incentive to control costs
- Requires trust
GMP variant is most common — combines cost transparency with owner protection against overruns.
Unit price
Contractor is paid based on quantities of work performed at unit prices:
- Site work — cubic yards of dirt moved
- Concrete — cubic yards placed
- Excavation — linear feet of trench
Best for: Site work and infrastructure where quantities are uncertain.
Time and materials
Contractor is paid for time spent and materials used:
- Hourly labor rates
- Material costs plus markup
- Best for: Small or undefined work
Contractor selection
Selecting the right contractor is critical to success.
Selection criteria
Experience:
- Similar project types
- Similar size and complexity
- Local market experience
- Track record of completed projects
Financial strength:
- Bonding capacity
- Banking relationships
- Working capital
- History of completed projects
Team:
- Project manager experience
- Superintendent experience
- Subcontractor relationships
- Available staff
References:
- Past owners
- Past architects
- Past lenders
- Subcontractors
Approach:
- Cost estimating quality
- Schedule realism
- Communication style
- Problem-solving approach
Pricing:
- Competitive but not lowest
- Includes appropriate contingency
- Realistic schedule
Selection process
Long list (5-10 contractors):
- Initial qualification
- Reference checks
- Project list review
Short list (3-4 contractors):
- Detailed proposal request
- Interviews
- Site visits to current projects
- Financial review
Selection:
- Best value (not just low bid)
- Owner-contractor fit
- Negotiate contract
Bidding process
For competitive bidding:
- Bid package preparation — complete documents, instructions, specifications
- Bid invitation — to qualified contractors
- Pre-bid meeting — site visit, questions
- Q&A period — written questions and answers
- Bid submission — sealed bids on a deadline
- Bid analysis — apples-to-apples comparison
- Negotiations — clarifications and refinements
- Award — selection and contract
Avoiding bid mistakes
Common bidding mistakes:
- Incomplete documents — bids include too much contingency
- Too few bidders — uncompetitive
- Low bidder selection — often the worst choice
- Inadequate scoping — surprises during construction
- Schedule pressure — hurried bids miss issues
Contract terms
A construction contract should address:
Scope
- Detailed description of what's being built
- Reference to drawings and specifications
- Inclusions and exclusions
Price
- Total contract price (lump sum or GMP)
- Allowances for undefined items
- Unit prices for variable quantities
- Payment terms (typically monthly progress)
- Retainage (typically 10% held until substantial completion)
Schedule
- Start date
- Substantial completion date
- Final completion date
- Milestones
- Liquidated damages for late completion (typically $500-$5,000/day)
- Bonus for early completion (sometimes)
Changes
- Change order procedures
- Pricing for changes (cost-plus markup or unit prices)
- Time extensions with changes
- Owner approval requirements
Delays
- Excusable delays (weather, force majeure, owner-caused)
- Inexcusable delays
- Extension of time procedures
- Compensable vs non-compensable delays
Quality
- Standards of workmanship
- Code compliance
- Inspection requirements
- Warranty period (typically 1 year minimum)
- Warranty repair obligations
Insurance and bonding
- General liability insurance ($1M-$5M minimum)
- Workers comp
- Builders risk insurance (often owner-provided)
- Performance bond (often 100% of contract value)
- Payment bond (protects subcontractors)
Risk allocation
- Indemnification
- Limitation of liability
- Hazardous materials
- Differing site conditions
- Subsurface conditions
Dispute resolution
- Direct negotiation first
- Mediation
- Arbitration or litigation
- Venue
Termination
- Termination for cause
- Termination for convenience
- Notice requirements
- Wrap-up procedures
Standard contract forms
Most commercial construction uses standard contract forms with modifications:
AIA contracts
- A101 — Owner-Contractor Agreement (lump sum)
- A102 — Owner-Contractor Agreement (cost plus with GMP)
- A201 — General Conditions (referenced in agreements)
- A102 is most common for commercial development
ConsensusDocs
- Alternative to AIA
- Developed by multi-stakeholder group
- More balanced between owner and contractor
Custom contracts
- Drafted by owner's attorney
- Tailored to specific project
- More negotiated terms
Construction phase management
Once construction starts, active management is essential.
Pre-construction tasks
Before construction begins:
- Pre-construction meeting with all key parties
- Permit verification
- Insurance verification
- Bond verification
- Submittal schedule establishment
- Site logistics plan
- Communication protocols
- Schedule baseline
Daily / weekly management
- Progress monitoring against schedule
- Quality monitoring
- Safety monitoring
- Issue identification and resolution
- Subcontractor coordination
- Inspection coordination
- Documentation of progress, issues, decisions
Owner participation
The owner should:
- Attend weekly meetings
- Walk the site weekly
- Review progress photos
- Approve change orders promptly
- Make decisions quickly when needed
- Maintain relationships with key contractor staff
Communication
- Weekly OAC meetings (Owner-Architect-Contractor)
- Daily contact between PM and superintendent
- Written communication of decisions
- Document everything
Schedule management
The schedule is one of the most important tools:
- Baseline schedule at contract
- Updates at least monthly
- Critical path identification
- Look-ahead schedules (3-week typical)
- Recovery plans for slippage
Cost management
- Budget vs actual tracking
- Forecast at completion
- Change order log
- Contingency tracking
- Cash flow projection
Change orders
Change orders are the biggest cost risk:
Sources of changes:
- Owner-directed changes (scope additions)
- Design changes (errors, omissions)
- Field conditions (unforeseen issues)
- Code interpretation changes
- Material substitutions
Managing changes:
- Authorize promptly to avoid delays
- Negotiate fairly but firmly
- Maintain change log
- Track impact on budget and schedule
- Use contingency wisely
A typical project will have 5-15% of construction cost in change orders. Your contingency should accommodate this.
Quality control
- Inspections by owner's rep, architect, third party
- Testing (concrete, soils, materials)
- Punch list generation
- Punch list completion
- Final inspections
Safety
- Contractor responsibility primarily
- Owner oversight
- OSHA compliance
- Safety incidents reporting
- Insurance compliance
Construction phases
Construction proceeds in phases:
Phase 1: Site work (weeks 1-8)
- Mobilization
- Surveying and staking
- Erosion control installation
- Demolition and clearing
- Earthwork (cut, fill, grading)
- Underground utilities
- Stormwater systems
- Foundations preparation
Phase 2: Foundation (weeks 6-12)
- Excavation
- Footings
- Foundation walls
- Slab on grade
- Underground plumbing rough-in
Phase 3: Vertical construction (weeks 10-30)
- Structural framing (steel, concrete, wood)
- Roof framing
- Roofing
- Exterior walls
- Windows and doors
- Exterior closure
Phase 4: MEP rough-in (weeks 18-32)
- HVAC ductwork
- Plumbing rough-in
- Electrical rough-in
- Fire sprinkler rough-in
- Inspections
Phase 5: Interior finishes (weeks 24-40)
- Drywall
- Painting
- Flooring
- Ceilings
- MEP trim out
- Doors and hardware
- Casework
- Fixtures
Phase 6: Site finishes (weeks 28-44)
- Paving (parking, drives)
- Curbs and sidewalks
- Striping
- Landscape installation
- Irrigation
- Site lighting
- Signage installation
Phase 7: Final completion (weeks 38-46)
- Final inspections
- Punch list completion
- Certificate of occupancy
- Owner training
- Closeout documents
Total construction duration for a typical 10,000 SF commercial building: 8-12 months.
Worked example: managing construction of a Lakeland retail center
You're managing construction of a 7,500 SF retail center plus 2 outparcels. Total construction budget: $4.2M. Schedule: 11 months.
Pre-construction
- Selected GC via competitive bid (3 bidders)
- AIA A102 contract with GMP of $4.2M
- 100% performance and payment bond
- 11-month schedule with $1,500/day liquidated damages
- Owner's project manager assigned
Month 1-2: Site work
- Mobilization and erosion control
- Demo of existing improvements
- Mass grading
- Underground utilities
- Stormwater pond construction
Month 3-4: Foundation
- Building pad preparation
- Footings and foundation walls
- Slab on grade
- Underground plumbing
Month 4-7: Vertical construction
- Steel structure
- CMU walls
- Roof
- Exterior closure
Month 6-9: MEP rough-in
- HVAC ductwork
- Plumbing
- Electrical
- Fire sprinklers
Month 8-10: Interior finishes
- Tenant build-outs (per individual lease specs)
- Painting and flooring
- Ceilings and finishes
Month 9-11: Site finishes
- Paving
- Striping
- Landscape
- Lighting
- Signage
Month 11: Closeout
- Final inspections
- Certificate of occupancy
- Tenant move-ins begin
Issues during construction
- 14 change orders totaling $185K (4.4% of original budget)
- 3-week weather delay
- 2-week supply chain delay (steel)
- Modest quality issues addressed via punch list
Outcome
- Substantial completion within 1 month of original schedule
- Total cost $4.39M (4.5% over original GMP, within contingency)
- All tenants moved in within 60 days of CO
- Owner satisfied with quality
This is what successful construction looks like: active management, controlled changes, on-time delivery, acceptable cost variance.
Common construction mistakes
- Selecting GC by low bid — best value beats lowest cost
- Inadequate documents at bid time — leads to changes
- Insufficient contingency — 5% is too low; use 10-15%
- Poor change management — undocumented or unapproved changes
- Inadequate owner involvement — issues missed
- Communication failures — assumptions not verified
- Weather and supply chain not accommodated in schedule
- Inadequate insurance and bonding
- Unfair contract terms that breed disputes
- Inadequate closeout — punch list lingering for months
What to take away
- Construction delivery methods: DBB, DB, CMAR, CM-Agent, IPD
- Contract types: lump sum, cost-plus, GMP, unit price, T&M
- CMAR with GMP is most common for active developer commercial projects
- Contractor selection: experience, financial strength, team, references, approach, price
- Best value beats lowest bid
- Contract terms: scope, price, schedule, changes, delays, quality, insurance, risk, disputes
- Pre-construction setup is critical
- Active owner management is essential
- Change orders typically 5-15% of contract; budget accordingly
- Schedule management includes baseline, updates, look-aheads, recovery
- Construction phases: site work, foundation, vertical, MEP rough-in, finishes, site finishes, closeout
- Common mistakes: low-bid selection, weak documents, inadequate contingency, poor management
Next lesson: development pro forma and feasibility math — the financial analysis that drives go/no-go decisions throughout development.